When our customer told us their needs, we had to develop a specific product. So, we have already worked closely with their technical team.
It has become a common challenge.
During the assembly, following the discovery of some restrictions, we change the pitch of the equipment, the width of the pads, the type of steel used and that in accordance with the expected delivery.
We had to skid the 33,000 pounds substation on 10km ramp.
For the weight saving while moving, we removed several parts deemed critical and reinstalled everything on site.
Cooperation between the client and our team allowed to bring the 4MVA in place, on time and with instant and safe startup.