Collahuasi lies in the far northeast of Chile, close to the border with Bolivia. Credit: Collahuasi.
Collahuasi’s reserves are held in three main orebodies; Ujina and Rosario, and the smaller Huinquintipa oxide deposit. Credit: Collahuasi.
Sulphide ore is treated by flotation to produce concentrates for export. Credit: Collahuasi.

Collahuasi copper mine is situated in northern Chile, about 180km southeast of the port of Iquique, at an altitude of 4,400m.

The mine is jointly owned by Anglo American (44%), Glencore (44%), and Japan Collahuasi Resources (12%). The operating company is Cia. Minera Doña Ines de Collahuasi.

Lying in an area of historical copper mining, the deposit was outlined in 1991 after exploration by Shell, Chevron and Falconbridge in the late 1980s. The mine was commissioned in April 1999 at a cost of $1.76bn. During 2004, the project partners completed a $584m expansion programme at the mine, giving it a long-term capacity of 500,000t/yr of copper.

The Collahuasi mine has up to 51 years of life from 2020 to 2070 according to the latest Life of Mine plan.

Geology and reserves

Collahuasi is based on a typical low-grade copper porphyry, comprising three ore zones: the major Ujina and Rosario deposits consisting of secondary, enriched sulphides and oxides and the Huinquintipa oxide deposit.

The major ore minerals are chalcocite, chalcopyrite and bornite. Oxide mineralisation occurs mainly as chrysocolla with minor brochantite, native copper, and copper-iron-manganese oxides and hydroxides.

The project’s previous shareholder Xstrata Copper announced a 28% increase in the total estimated mineral resource at the mine in 2008, representing the equivalent of an additional 11 million tonnes of contained copper metal from 2007 resources.

The mine was estimated to contain total measured and indicated resources of 5,391Mt grading at 0.81% of copper as of December 2019. The proved and probable reserves totalled 3,055Mt grading at 0.92% copper.

The mine life for mineral reserves is up to 10 years and for mineral resources is up to 18 years.

Open-pit mining

The Ujina and Huinquintipa zones were mined first, with a transition to the Rosario orebody completed during 2004. Stripping at Rosario began in 2002 and the stripping ratio at Ujina averages 4.4:1 (waste: ore) with a 15m bench height. Huinquintipa is somewhat smaller. The design mining rate of 360,000t/d of rock was achieved in Year 1, involving the blasting of 750,000t of material every two days.

Equipment used at Collahuasi includes five Bucyrus-Erie 49R III electric drills and a Drilltech T60KL diesel drill, 40 Komatsu 830E haul trucks and five Bucyrus-Erie 495BI electric rope shovels. Two Krupp Fördertechnik 6,000t/hr semi-mobile crushing plants, one used in each pit initially, provide substantial in-pit haulage cost savings.

Processing

The processing area consists of both oxide and sulphide plants. Oxide and mixed ores are treated by heap-leaching, solvent-extraction and electro-winning (SX-EW). Sulphide ore is crushed, ground and treated by flotation.

“The mine was estimated to contain total measured and indicated resources of 5,391Mt grading at 0.81% of copper as of December 2019.”

Run-of-mine sulphide ore enters the primary gyratory crusher prior to transport to two parallel grinding circuits, each consisting of a SAG mill and a ball mill. Secondary closed-circuit grinding includes cyclone classifiers, from which the overflow feeds the flotation circuit. The flotation concentrate is thickened to 50% solids for slurry transport in a 200km-long pipeline to Punta Patache, 65km south of Iquique, where it is thickened and filtered before shipment worldwide. An expansion to the concentrator was completed during 2004.

Run-of-mine oxide ore is reduced to -10mm by three-stage crushing. The fine ore is agglomerated with sulphuric acid and water before being conveyed to the leach pads. Copper is recovered from the pregnant leach solution in the solvent-extraction plant, where the copper is stripped using organic solutions; the stripped liquor is then returned to the leach pads for re-use.

The strip solution is cleaned using dilute acid and flotation, and is filtered prior to the electro-winning phase, where the copper is plated onto electrolysis cathodes. These are stripped by the Kidd process on a seven-day cycle, the cathode copper being transported by road to Iquique for export.

Production

In 2005, Cia Minera Doña Inés de Collahuasi produced 488,600t of copper in concentrate, plus 68,600t of cathode copper. In December 2005, the company commissioned a $36m molybdenum recovery plant that has a capacity of 7,500t/y of contained moly.

In January 2008, the company announced an upgraded mineral resource of 5.19 billion tonnes at an average grade of 0.83% copper, including, for the first time, 746 million tonnes at a grade of 1.06% from the Rosario Oeste deposit.

This compares to the previous mineral resource of 4.05 billion tonnes at an average grade of 0.80% copper. The mineral resource includes ore reserves of 2.20 billion tonnes at a grade of 0.82% copper, a 25% increase in tonnage from ore reserves of 1.76 billion tonnes at 0.89% copper from December 2006.

The mine produced 565,400t of fine copper from 87.25 million tonnes of ore in 2019.

Power supply for the Collahuasi copper mine

Enel Generación was awarded a 10-year power supply contract to supply 100% renewable energy for the copper mine, with effective from April 2020.

Environment at Collahuasi

As the environment at Collahuasi is harsh and fragile, ecological issues have a top priority. Collahuasi is a zero-discharge operation, with much of its water being recycled. An extensive environmental monitoring system is in place along with research projects in high altitude operations.

Collahuasi achieved its ISO 14001 environmental management certification in 2000.