Boss Energy begins mining uranium at Honeymoon project

The Honeymoon project was previously owned by Uranium One and acquired by Boss Energy in 2015.

Surya Akella October 11 2023

ASX-listed uranium company Boss Energy has started mining activities at its Honeymoon project near the town of Broken Hill in South Australia.

The launch of mining activities was achieved with pre-conditioning of the first wellfield. It will lead up to in-situ recovery feeding of the processing plant with extracted uranium in the last quarter of this year.

The process of pre-conditioning cleans the unwanted chlorides and calcium from the orebody for efficient leaching and uranium capture.

Calcium and chloride containing groundwater is pumped from the orebody via extraction wells and processed through the water treatment plant to remove calcium.

It is then passed through the reverse osmosis (RO) plant to remove chloride. This clean water is thereafter acidified before being reinjected into the orebody through injection wells.

To reach the milestone, the company completed major construction work including wellfield development, gypsum repository construction, water treatment and RO plant commissioning. With these milestones, the mine is on track to begin production in December of this year.

Boss Energy managing director Duncan Craib said: “It is a testament to the hard work and effort undertaken by all Boss employees over many years to reach today’s pivotal milestone, the commencement of mining activities on Honeymoon.”

The project hosts the historical Honeymoon uranium mine, which was the country’s second in-situ recovery uranium mine. The project’s previous owner was Uranium One, which had initially began operations in 2011.

However, operations at the mine were halted in November 2013 due to a slump in the price of uranium. Subsequently, the project was acquired by Boss Energy in 2015.

An enhanced feasibility study released in June 2021 included revised capital and operating estimates and a wellfield design plan, along with revised economic assumptions.

Resource estimates at the Honeymoon restart area (HRA) have indicated 36 million pounds of triuranium octoxide (U3O8). With a life of mine of more than ten years, the production rate has been forecast at 2.45 million pounds per annum.

The company also claims that there is a further 35.6 million pounds outside of HRA, with significant potential for exploration.

Critical minerals are key to transitioning to a low-carbon world

Over 70 countries have set net-zero targets, and even more have pledged to lower their emissions. However, these widespread objectives for a greener future are straining supplies of natural resources. Deposits of critical minerals are typically found in specific regions of the world. The race to control these mineral assets has led to intense rivalries between China, the US, and the EU, with China currently dominating the mineral supply chain and the development of energy transition technologies.

Newsletters by sectors

close

Sign up to the newsletter: In Brief

Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Thank you for subscribing

View all newsletters from across the GlobalData Media network.

close