Canada-based Kinross Gold is to begin a phase one expansion of its Tasiast gold mine in Mauritania.
The open-pit mine processes ore through an 8,000t-per-day mill and dump leach.
Kinross plans to invest about $300m to increase the mill’s throughput capacity from the existing 8,000 tonnes per day (t/d) to 12,000t/d.
The capacity will be increased by the addition of a gyratory crusher, a SAG mill and three leach tanks, as well as improvements to other components of the processing circuit.
During the first ten years from 2018-2027, the new mill is expected to produce an approximate average of 409,000 gold ounces a year.
Kinross also plans to enhance incremental crushing and grinding capacity for the existing carbon-in-leach (CIL) circuits.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataPhase one is expected to reach full production by the end of first quarter of 2018.
Kinross Gold president and CEO Paul Rollinson said: "This phased approach allows Kinross to transform Tasiast into a lower-cost, cash flow-positive operation in the near term, while preserving the operation’s significant growth potential.
"The expansion is forecast to reduce Tasiast’s production cost of sales per ounce by an estimated 48% while increasing annual production by an estimated 87% compared with 2015."
During phase two, the total throughput is expected to increase to 30,000t/d.
Rollinson added: "The two-phased approach strikes the right balance between growth and preserving balance sheet strength and is well-suited to the current gold price environment."
Phase one commissioning is expected to begin in late 2017, while full production is expected to start in early 2018.