Rio Tinto will provide an additional $1.3bn for the development of the Simandou iron ore project in Guinea.
The firm will invest $211m in continued studies and $1.1bn in commitments for early works and procurement of long-lead items of the project.
Currently the firm is in the process of obtaining the required regulatory approvals with project partner Chalco.
Finalisation of the infrastructure investment framework is expected in early 2012, which will also require the Government of Guinea to contribute its share of infrastructure project expenditure.
The funding will allow the project to move forward towards a first shipment of ore in mid-2015.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalData